Update June 13th, 2022

June 13th, 2022

2022-05-13-16_22_54-clipboard
mto-relocation

Work on the future Ministry of Transportation Patrol Yard continues with foundation and grading work continuing in preparation for the sand dome footings.

Planned activities for the week of June 13th include on-going Earthworks within the Tailings Management Facility, drilling, blasting, foundation work and the start of steel erection within the Plant Site area, drilling, blasting and placement of rock for the Highway 11 Realignment, and the installation of power lines and road construction. 

What's coming next:

Greenstone Mine will be conducting scheduled blasts within the Project Area and within the Highway 11 Realignment Area. Blasting will occur on a regular basis during the construction and operations phases of the Project. Blasting Notices are posted on the website homepage. Enbridge Gas Inc. (EGI) blasting notices will be posted on the Greenstone Mine website homepage. Greenstone Mine is not responsible for any EGI blast delays or cancellation that are not reflected on the website homepage.

‘No Trespassing’ signs within the former Barton Bay Trail area due to work activities being undertaken for the construction of the Highway 11 Realignment have been installed for everyone’s safety as this work continues. With the MHT pump well building in place, pumping of historical tailings water to the Temporary Effluent Water Treatment Plant is underway. Earthworks in the Kenogamisis Pit located North of Highway 11 behind Between Bridges Inn will continue with loading and hauling of pit run material to the future Plant Site area as needed. Concrete installation is on-going within the future permanent Truck Shop, Process Plant west end and the Power Plant. Structural steel for the Truck Shop continues to arrive. Interior work for the Effluent Water Treatment Plant continues. First and second floor complexing of the Administration Building continues, with exterior siding being installed. M1 Pond preparations for liner installation continues. Temporary Power Line work will continue within the future Plant Site area.

Ongoing hauling of material from the S4 Aggregate Pit to the Goldfield Creek Dam, and management of water in both the Tailings Management Facility (TMF) and Goldfield Creek areas is ongoing.

Work will continue on the Highway 11 widening near the Main Access Road in early June. Work will take approximately one month with lane reductions in place for much of that time. Traffic management protocols will be in place according to Ontario Ministry of Transport requirements. Please obey the signals of all flagpersons.

Drilling, blasting and crushing within the future Highway 11 Realignment footprint (west side) will continue. Placement of materials continues east of Michael Power Boulevard. With the Michael Power Boulevard Crossing in use, motorists are asked to obey the 60 km/h maximum speed limit and to proceed with caution.  Work within the future MTO Patrol Yard continues with foundation work continuing and grading work commencing in preparation for the sand dome footings.

Construction in and around Greenstone Mine involves the use of heavy equipment such as zoom booms, cranes, drills, excavators, skidders, wood chippers, bulldozers, tri-axle haul trucks, articulated trucks and loaders. For health and safety reasons, we caution the general public to follow and obey all posted signs across the Project area.

The safety of our employees, contractors and the general public is paramount as we construct the Greenstone Mine.

Work on the construction of Enbridge’s 13 kilometre (km) 6-inch diameter steel natural gas pipeline to provide the project with clean, affordable natural gas has started.  More information on Enbridge’s project can be found here: https://www.enbridgegas.com/about-enbridge-gas/projects/greenstone-pipeline-project